Friday, July 28, 2006


Chubb are on site with the fire extinguishers Posted by Picasa

It's beginning to look like an office now... Posted by Picasa

The chairs are now on site Posted by Picasa
Defects

I've created a second site, for which there is a link on the right. This will be the defects list and will be updated as things get picked up.
Ports are being kroned downstairs

Ports are finished in the training room
 Posted by Picasa

Thursday, July 27, 2006

Alex is a little concerned that the carpet upstairs is looking a bit irregular and worn when compared to downstairs



Vinyl in the upstairs kitchen
 Posted by Picasa



 Posted by Picasa



 Posted by Picasa
The islands are forming...



The desks upstairs
 Posted by Picasa
The furniture has arrived and assembly is underway
 Posted by Picasa

The carpeting has been done in Alex's office, using the best of the original carpest tiles. And whilst it looks ok, there is a noticable difference between it and the new carpet.
 
This will now be replaced with new tiles

Wednesday, July 26, 2006


The carpeting in the main floor has been done, just Alex's office left.
 Posted by Picasa

The racks are starting to fill up...

Samples for the kitchen floor Posted by Picasa
Alex has chosen number 3, light oak

The carpeting has started going down Posted by Picasa

Power sockets on the drops have been done

Power sockets against the walls are under way

Termination of the drops should be finished today

Termination in the rack has begun Posted by Picasa

Painting downstairs is complete bar the odd finishing touch Posted by Picasa

Monday, July 24, 2006


The painting downstairs is almost complete



The server stuff has arrived, me and graham should be testing them today.
 Posted by Picasa